Jinneng Power's Electric water feeding pump retrofit project by using two HIVERT 6kV 4500kVA (AFWF), successfully completed on the 30th of Oct., without stopping the pumps during the whole process!

views:   date:2020-11-2 11:12:52

On October 30, the 2*300MW circulating fluidized bed direct air cooling unit (cogeneration of heat and power) of Shanxi Guojin Coal Power Co., LTD., Jinneng Electric Power Holding Group, and the conversion transformation project of electric feed water pump of Unit 2, 21 and 23, was officially completed. This project adopts the innovative technical renovation scheme of "construction without stopping", which creates the first transformation project of the electric feed pump without stopping converter in the power industry of China's frequency conversion industry, and sets a model in the frequency conversion industry of China.

煤電公司封面.jpeg


Shanxi Guojin Coal Power Co., LTD. (hereinafter referred to as "Guojin Coal Power") of Jinneng Power Holding Group is equipped with two 300MW circulating fluidized bed direct air cooling units (cogeneration of heat and power) with a total capacity of 600MW. The single machine water supply system is equipped with three 35%MCR capacity electric feed pumps, which operate in parallel and with hydraulic couplers for speed regulation. The power consumption rate of electric feed water pump accounts for 3% of the power consumption, and the energy consumption is high.


At the end of the 13th Five-Year Plan period, the power plant responded to the national call for energy conservation and emission reduction. After the preliminary feasibility study and demonstration, the plant decided to install one 6KV/4500KVA air-water-cooled VFD of Hiconics for each of the 21 and 23 electric feeders in unit 2. The original 22 electric feeders would not be modified and the power frequency would be reserved to achieve the purpose of energy conservation.


In order to ensure that the power plant starts heating before the two VFDs are fully operational, After field investigation, Hiconics and Guojin Coal-power set a high efficient and practical construction plan, the innovation of the "non-stop" construction scheme of reformation are put forward: the ensure power plant unit 2 of the 3 electric feed water pump in the normal operation of the electric pump is 2, under the condition of high efficiency construction transformation service 21 electric feed water pump; After the first frequency converter is successfully put into operation on site, the construction and transformation of the no. 23 electric feed water pump which is out of service shall be carried out timely to ensure that the frequency conversion transformation of the electric feed water pump of unit 2 of the power plant will be completed within the given time node.

WechatIMG101.jpeg


WechatIMG102.jpegWechatIMG103.jpeg

WechatIMG104.jpeg

WechatIMG106.jpeg


The whole reconstruction process of the project is difficult and risky. The project team of Hiconics always makes great efforts to complete tasks with high efficiency and high quality. The modified electric feed water pump can still meet the requirements of automatic water supply control under any load under the operation condition of one variable operation and two variable operations, and the control effect is better than that at power frequency.


The conversion and energy saving renovation project of electric feed water pump of Unit 2 of Guojin Coal Power Co., LTD lasted 30 days from the start of civil construction to the smooth operation of equipment. Since the field converter was put into operation, the operation indexes of the electric feed water pump after modification have all met the requirements of efficient operation of Unit 2. According to the test data of the control room of the power plant, since the frequency conversion transformation of the electric feed pump of unit 2 was put into operation, the power saving rate of the electric feed pump reached 24-27%, the power consumption rate of the plant decreased by 0.6%, and the energy saving effect exceeded expectations.


Service is the key factor of communication between enterprises and customers. Over the years, Hiconics always stands in the perspective of the user, and tries its best to solve all the problems encountered by the customer, and solve the equipment problems for the customer in the first instance, so as to ensure the smooth production. With Hiconics's expertise in VFD and automation, Guojin Coal-power has achieved significant improvement in quality control, efficient operation, safety and reliability, providing a solid guarantee for the power plant to realize energy conservation and emission reduction


Hiconics Eco-energy Technology Co., Ltd.

Address:NO.3 Boxing 2nd Road,Economic and Technological Development Zone,Daxing District, 100176,Beijing, China

E-mail:claire_deng@midea.com

TEL:+86 10 5918 0185

FAX:+86 010-59180035

Copyright 2006-2017     
all right reserved:Hiconics Eco-energy Technology Co., Ltd.      京ICP備05028480-1      京公網備110301000391      Support:北京網站建設

2020精品国产不卡,国产精品免费,国产+精品+自在+线,青草青草久精品视频 99久热精品免费观看动漫 99热国产这里只有的精品9 99精品在线视频 99热这里只有精品 国产精品综合色区 久久热这里都是精品 精品cosplayr18cos 国产精品欧美 九九热线有精品视频35 岛国精品写真电影网 欧美精品xxxx 国产精品每日更新 九九九热这里只有精品视频 欧美精品第50页 九九视频精品 久久爱精品视频 精品国产美女剃毛 精品国精品国产自在久国产 青草青草久热这里只有精品 欧美日韩国产精品 国内精品免费视频自在线拍 国产精品第一页 99热这里只有精品最新地址获取 99热国产这里只有的精品9 这里有精品 色吊妞视频这里有精品 开放90后国产精品四虎 亚洲精品色在线网站 这里都是精品 青娱乐精品视频 久热精品在线 国产精品高清喂奶 精品软件共享区 99久热精品免费观看四虎 山外人精品影院 成人精品 99re 久久这里只有精品首页 99精品在线观看 青娱乐精品视频 自拍精品 色吊妞视频这里有精品 精品软件共享区 精品韩国三级在线观看视频 欧美一级精品视频 精品丝袜国产自在线拍 国产精品综合色区 国产精品亚洲 国产在线精品二区 国内揄拍国内精品 精品国自产拍天天更新 99国产这里只有精品视频